What the CAG’s reports record
How the scheme was set up, as the Comptroller and Auditor General’s
reports state it, cited to the printed page. Never what an audit found.
| Began | January 2010; 20,000 MW grid and 2,000 MW off-grid solar by 2022 named in the report “Jawaharlal Nehru National Solar Mission” | Comptroller and Auditor General of India, Report No. 34 of 2015, Renewable Energy Sector in India, Union Government, Ministry of New and Renewable Energy, para 3.2, p. 32. |
| Began | January 2010; target 20,000 MW by 2022 | Comptroller and Auditor General of India, Report No. 29 of 2017, Competitiveness of BHEL in Emerging Markets, Union Government, para 3.1.1, p. 5. |
| Began | January 2010 named in the report “National Solar Mission” under Ministry of New and Renewable Energy | Comptroller and Auditor General of India, Report No. 13 of 2025, Solar Parks and Ultra Mega Solar Power Projects, Union Government, Chapter I (Introduction), p. 1. |
| Coverage | target 20,000 MW by 2022, raised to 1,00,000 MW in July 2015 named in the report “National Solar Mission” | Comptroller and Auditor General of India, Report No. 13 of 2025, Solar Parks and Ultra Mega Solar Power Projects, Union Government, Executive Summary, p. v. |
What myScheme says
| myScheme record | ... no entry found in the 2026-10-17 snapshot, under a generous name match | ... |