The scheme aims to promote the manufacturing of high-efficiency solar photovoltaic modules and reduce import dependence. Through this scheme, Production Linked Incentive is provided to eligible manufacturers.
In detail
The scheme “Production Linked Incentive Scheme Tranche-I under National Programme on High Efficiency Solar PV Modules" has been implemented by the Ministry of New and Renewable Energy, Government of India. It aims to promote the manufacturing of high-efficiency solar photovoltaic modules in India and reduce import dependence on renewable energy. Through this scheme, Production Linked Incentive (PLI) is provided to eligible manufacturer-beneficiaries for sales of high-efficiency solar photovoltaic modules, based on sales volume, performance parameters, and local value addition. The scheme is implemented by the Ministry of New and Renewable Energy through the Indian Renewable Energy Development Agency (IREDA). The scheme has a financial outlay of ₹4,500 crore over 5 years and supports domestic manufacturing capacity, technology adoption, integrated plants, sourcing of local material, and employment generation. Beneficiaries are selected through a transparent bidding process, and incentives are disbursed annually, subject to scheme conditions
> Objectives:
- To build up solar PV manufacturing capacity of high-efficiency modules.
- To bring cutting-edge technology to India for manufacturing high-efficiency modules. The scheme will be technology agnostic in that it will allow all technologies. However, technologies that will result in better module performance will be incentivised.
- To promote the setting up of integrated plants for better quality control and competitiveness.
- To develop an ecosystem for the sourcing of local material in solar manufacturing.
- Employment generation and technological self-sufficiency.
Who qualifies
- The applicant should be a manufacturer proposing minimum integration across solar cells and modules.
- The applicant should undertake to set up a manufacturing plant of minimum 1,000 MW capacity.
- The applicant should meet minimum module performance parameters:
- Minimum module efficiency of 19.50% with temperature coefficient better than -0.30% per degree Celsius; or
- Minimum module efficiency of 20% with temperature coefficient equal to or better than -0.40% per degree Celsius.
- The applicant may be a single company or Joint Venture/Consortium, subject to scheme conditions.
- The applicant may be a Greenfield project. Brownfield projects may participate subject to prescribed eligibility criteria.
What you get
> Incentive Benefit:
- Production Linked Incentive (PLI) to eligible manufacturers.
- Financial outlay: ₹4,500 crore.
- PLI available for 5 years from commissioning or scheduled commissioning date, whichever is earlier.
- PLI calculation formula:
- PLI (₹) = Sales Volume (Wp) × Base PLI Rate (₹/Wp) × Tapering Factor × Local Value Addition.
> Additional Benefit Conditions:
- PLI amount increases with increased local value addition.
- Brownfield projects are eligible, but the PLI rate is 50% of the Greenfield rate.
- PLI rates are subject to tapering factors:
- Year 1: 1.4
- Year 2: 1.2
- Year 3: 1.0
- Year 4: 0.8
- Year 5: 0.6
Who is excluded
- The applicant shall not have availed benefits under MNRE tenders linked to photovoltaic manufacturing.
- The applicant shall not have availed benefits under SIPS/M-SIPS of the Ministry of Electronics and Information Technology.
- The applicant shall not have imported capital goods for setting up the module manufacturing facility before the last date of bid submission.
not about the scheme.
Provenance
| schemeName | Production Linked Incentive Scheme Tranche-I under National Programme on High Efficiency Solar PV Modules | myScheme · 2026-09-02 |
| schemeOpenDate | ... | not published at source |
| schemeCloseDate | ... | not published at source |
| nodalMinistryName | Ministry Of New and Renewable Energy | myScheme · 2026-09-02 |
| dbtScheme | ... | myScheme · 2026-09-02 |
| achievement data | ... | no source publishes this for any central scheme |