Scheme for Development of Solar Parks and Ultra Mega Solar Power Projects
Named by 1 government source(s), and not listed on myScheme
CAG audit reportsNot on myScheme
No documentation checks for this scheme
The nine checks measure what myScheme publishes about a scheme. There is no myScheme
record here to measure, so this page shows none. A score of nought would read
as a verdict on the scheme when it is a fact about the portal.
What the CAG’s reports record
How the scheme was set up, as the Comptroller and Auditor General’s
reports state it, cited to the printed page. Never what an audit found.
| Began | December 2014 (Phase I) named in the report “Solar Park Scheme, Phase I” | Comptroller and Auditor General of India, Report No. 13 of 2025, Solar Parks and Ultra Mega Solar Power Projects, Union Government, para 1.2.1, p. 4. |
| Began | March 2017 (Phase II) named in the report “Solar Parks and Ultra Mega Solar Power Projects (Solar Park Scheme, Phase II)” under Ministry of New and Renewable Energy | Comptroller and Auditor General of India, Report No. 13 of 2025, Solar Parks and Ultra Mega Solar Power Projects, Union Government, para 1.2.2, p. 5. |
| Implemented by | Solar Energy Corporation of India, nodal agency, paid one per cent of the Central Financial Assistance named in the report “Solar Park Scheme” under Ministry of New and Renewable Energy | Comptroller and Auditor General of India, Report No. 13 of 2025, Solar Parks and Ultra Mega Solar Power Projects, Union Government, para 5.1, p. 56. |
What myScheme says
| myScheme record | ... no entry found in the 2026-10-17 snapshot, under a generous name match | ... |